Vladivostok is in full swing recovery tram route number 6 «Sakhalin — Mine town.»
As the director of «Electric Vehicles» Lily Kozlov on the street. Borisenko already laid 1.9 km of tram tracks on the single track.
Today, May 20 Mayor Igor Pushkarev personally examined how workers cope with the task.
«Work on the reconstruction of tram tracks do not stop even for a day, and some are even ahead of schedule , — Said Igor Pushkarev. — We clearly set to run traffic on the six routes in the shortest possible time, because this is where the tram is on place and people need. »
Recall that the complete restoration of the tram route number 6 is scheduled for completion by September.